Shop Online And Raise Funds For Us At The Same Time

Tuesday, 24 May 2011

Meanwhile Back at the Building Site


While trustee Andy Conroy has been playing with a boat in the Bay of Biscay conctruction work has been pressing on apace at the House of Joshua building site.

The foundations have now been dug and concreted and the 34 support pillars for the ground floor have been formed. The next step will be to fill the gaps between the posts with concrete blocks to form the walls before installing the first floor support joists and then making the pillars for the upper storey.

This second stage will cost around £10,000 and we will be sending out the money for that within the next few days so that work can continue without interruption.
Bookmark and Share

No comments:

Post a Comment